Central Yungay
Located in Cabrero in the Biobío region and connected to the Charrúa substation, International Power Services Chile’s Yungay thermal plant began operations between 2007 and 2008. Located on 16.4-hectare site, it has a generated capacity of 199 MW and 2.6 km of its own transmission lines.
PLANT OVERVIEW
Yungay is integrated into the SEN, a system comprised of the former Central Interconnected System (SIC) and the Northern Interconnected System (SING), which extends from Arica to Chiloé. Central Yungay serves as a reliable backup plant, and its operation depends primarily on market demand, emergency situations, or instability in the electrical system.
- Commissioned in 2007 and 2008
- Dual-fuel thermal plant
- 199 MW of generated capacity
PLANT SPECIFICATIONS
thermal
Yungay’s thermal energy is generated from three diesel-gas units and one diesel-only unit, with the energy it generates being transported from the Yungay substation to the Charrúa transmission node via a 154 kV line.
It is comprised of:
- Three Mitsubishi (formerly Pratt & Whitney) diesel-gas units in SwiftPac
- FT8-3 configuration (2 turbines + 1 generator per unit)
- One General Electric diesel unit.
community news
Through outreach programs, hosted activities, and a steadfast presence, IPS Chile is dedicated to being an active member of the Biobío community.